491 Gerard Avenue

491 GERARD AVENUE (Boro: 2, Block: 2351, Lot: 7501)
Bronx

Duration

Total Duration:10.1 years
Start Date:May 2008
End Date:Jul 2018

Identifiers

Project ID:58638
Building ID:973182

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
200820102012201420162018202020222024ActualOfficial491 Gerard Avenue491 GERARD AVENUE(Boro: 2, Block: 2351, Lot: 7501)Bronx10.1yrs2.0yrs

Timeline Events (11)

May 14, 2008
City Map Amendment + Zoning Map Amendment (Contemplated) + Zoning Text Amendment (Contemplated) [P2009X0108] EAS Date
May 14, 2008
⚠️ Zoning Text Amendment + Zoning Map Amendment [P2009X0199] Positive Declaration (EIS Required)
Aug 21, 2012
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_16HPD019X] Earliest EAS Work (Phase I ESA)
Jul 13, 2015
Earliest DOB Filing
Oct 15, 2015
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_16HPD019X] Lead Agency Letter
Dec 02, 2015
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_16HPD019X] EAS Date
Dec 14, 2015
✅ Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_16HPD019X] Negative Declaration
Jun 23, 2016
HPD Financing ("Project Start")
Nov 09, 2016
Fully Permitted
May 25, 2018
Certificate of Occupancy
Jul 05, 2018
Building Completion (HPD)