MLK PLAZA

869 EAST 147 STREET (Boro: 2, Block: 2600, Lot: 7501)
Bronx

Duration

Total Duration:3.0 years
Start Date:Mar 2016
End Date:Mar 2019

Identifiers

Project ID:60810
Building ID:972899
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficial
MLK PLAZA869 EAST 147 STREET(Boro: 2, Block: 2600, Lot: 7501)Bronx3.0yrs1.9yrs

Timeline Events (9)

Mar 09, 2016
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2015X0275] Earliest EAS Work (Site Survey)
May 06, 2016
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2015X0275] Lead Agency Letter
Aug 16, 2016
Earliest DOB Filing
Oct 14, 2016
Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2015X0275] EAS Date
Oct 14, 2016
✅ Zoning Map Amendment + Zoning Text Amendment + Funding Programs (Contemplated) [P2015X0275] Negative Declaration
Apr 05, 2017
HPD Financing ("Project Start")
Apr 26, 2017
Fully Permitted
Mar 07, 2019
Certificate of Occupancy
Mar 07, 2019
Building Completion (HPD)