Duration
Total Duration:7.6 years
Start Date:Nov 2015
End Date:Jun 2023
Identifiers
Project ID:61575
Building ID:972764
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Nov 01, 2015
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0353] Earliest EAS Work (Phase I ESA)
Oct 14, 2016
Earliest DOB Filing
Nov 22, 2016
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0353] Lead Agency Letter
Nov 23, 2016
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0353] EAS Date
Nov 28, 2016
✅ Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015K0353] Negative Declaration
Apr 27, 2018
HPD Financing ("Project Start")
Mar 29, 2019
Fully Permitted
Aug 19, 2021
Certificate of Occupancy
Jun 08, 2023
Building Completion (HPD)