BRIDGE.425 E 161ST ST. MELROSE SITE C SHLP PORTION
425 EAST 161 STREET (Boro: 2, Block: 2383, Lot: 39)
Bronx
Duration
Total Duration:7.2 years
Start Date:Mar 2011
End Date:May 2018
Identifiers
Project ID:48643
Building ID:972670
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (12)
Mar 01, 2011
City Map Amendment + Zoning Map Amendment + Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc [P2013X0423] Earliest EAS Work (Phase I ESA)
Sep 11, 2014
Earliest DOB Filing
Oct 09, 2014
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2012X0204] Lead Agency Letter
Oct 09, 2014
Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2012X0204] EAS Date
Oct 09, 2014
✅ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2012X0204] Negative Declaration
Oct 09, 2014
City Map Amendment + Zoning Map Amendment + Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc [P2013X0423] Lead Agency Letter
Oct 09, 2014
City Map Amendment + Zoning Map Amendment + Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc [P2013X0423] EAS Date
Oct 09, 2014
✅ City Map Amendment + Zoning Map Amendment + Udaap Designation + Disposition City Owned Property + Zoning Special Permit Cpc [P2013X0423] Negative Declaration
Jun 29, 2016
HPD Financing ("Project Start")
Aug 03, 2016
Fully Permitted
May 10, 2018
Certificate of Occupancy
May 10, 2018
Building Completion (HPD)