Duration
Total Duration:7.3 years
Start Date:Sep 2011
End Date:Dec 2018
RFP Information
Seward Park RFP
Identifiers
Project ID:52122
Building ID:972598
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property + Zoning Map Amendment + Special Permit Bsa [P2014M0451] Positive Declaration (EIS Required)
Sep 07, 2011
Zoning Special Permit Cpc + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + City Map Amendment + Acquisition City Property [P2012M0292] Lead Agency Letter
Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + City Map Amendment + Acquisition City Property [P2012M0292] Positive Declaration (EIS Required)
Jan 09, 2013
RFP Release: Seward Park RFP
Sep 18, 2013
✅ RFP Designation: Seward Park RFP
Aug 01, 2014
Zoning Special Permit Cpc + Zoning Special Permit Cpc + Disposition City Owned Property + Udaap Designation + Zoning Map Amendment + Zoning Text Amendment + City Map Amendment + Acquisition City Property [P2012M0292] Earliest EAS Work (Phase IB Archaeological Survey)
Sep 30, 2014
Earliest DOB Filing
Jun 30, 2015
HPD Financing ("Project Start")
Nov 16, 2015
Fully Permitted
Dec 27, 2018
Certificate of Occupancy
Dec 27, 2018
Building Completion (HPD)