SENDERO VERDE A
50 EAST 112 STREET (Boro: 1, Block: 1617, Lot: 7502)
Manhattan
Duration
Total Duration:8.7 years
Start Date:May 2016
End Date:Feb 2025
RFP Information
SustaiNYC RFP
Identifiers
Project ID:63974
Building ID:972163
Data Quality Note
0-18 (Poor)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (7)
May 23, 2016
RFP Release: SustaiNYC RFP
Nov 10, 2016
⚠️ Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property + Acquisition City Property + Zoning Special Permit Cpc [P2017M0259] Positive Declaration (EIS Required)
Feb 07, 2017
✅ RFP Designation: SustaiNYC RFP
Jan 31, 2019
Earliest DOB Filing
Aug 30, 2019
Fully Permitted
Jun 24, 2021
HPD Financing ("Project Start")
Feb 06, 2025
Building Completion (HPD)