LIVONIA PHASE II SITES 6-8

487 LIVONIA AVENUE (Boro: 3, Block: 3800, Lot: 7501)
Brooklyn

Duration

Total Duration:6.2 years
Start Date:Dec 2012
End Date:Feb 2019

RFP Information

Livonia Avenue Initiative Phase II RFP

Identifiers

Project ID:54909
Building ID:971874

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2012201420162018202020222024ActualOfficialLIVONIA PHASE II SITES 6-8487 LIVONIA AVENUE(Boro: 3, Block: 3800, Lot: 7501)Brooklyn6.2yrs2.6yrs

Timeline Events (11)

Dec 01, 2012
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2013K0263] Earliest EAS Work (Phase I ESA)
Jun 14, 2013
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2013K0263] Lead Agency Letter
Jun 14, 2013
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2013K0263] EAS Date
Jun 14, 2013
✅ Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2013K0263] Negative Declaration
Apr 07, 2014
RFP Release: Livonia Avenue Initiative Phase II RFP
Dec 04, 2014
✅ RFP Designation: Livonia Avenue Initiative Phase II RFP
Nov 16, 2015
Earliest DOB Filing
Jun 30, 2016
HPD Financing ("Project Start")
Oct 19, 2016
Fully Permitted
Feb 22, 2019
Certificate of Occupancy
Feb 22, 2019
Building Completion (HPD)