FOX STREET PRC

1000 FOX STREET (Boro: 2, Block: 2724, Lot: 7502)
Bronx

Duration

Total Duration:3.3 years
Start Date:Feb 2016
End Date:Jun 2019

Identifiers

Project ID:60249
Building ID:971150

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficialFOX STREET PRC1000 FOX STREET(Boro: 2, Block: 2724, Lot: 7502)Bronx3.3yrs2.4yrs

Timeline Events (9)

Feb 11, 2016
Earliest DOB Filing
Mar 16, 2016
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_16HPD145X] Earliest EAS Work (Site Survey, Noise Monitoring, Phase I ESA)
May 19, 2016
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_16HPD145X] Lead Agency Letter
Sep 15, 2016
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_16HPD145X] EAS Date
Sep 16, 2016
✅ Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_16HPD145X] Negative Declaration
Dec 23, 2016
Fully Permitted
Dec 30, 2016
HPD Financing ("Project Start")
Jun 05, 2019
Certificate of Occupancy
Jun 05, 2019
Building Completion (HPD)