PROJECT RENEWAL.2865 CRESTON AVE.BEDFORD GREEN HOU
2865 CRESTON AVENUE (Boro: 2, Block: 3319, Lot: 56)
Bronx
Duration
Total Duration:6.8 years
Start Date:Mar 2015
End Date:Dec 2021
Identifiers
Project ID:60327
Building ID:971011
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Mar 01, 2015
Hpd Construction Financing [NO_ZAP_17HPD048X] Earliest EAS Work (Phase I ESA)
Aug 20, 2016
Earliest DOB Filing
Jan 17, 2017
Hpd Construction Financing [NO_ZAP_17HPD048X] Lead Agency Letter
Apr 01, 2017
Hpd Construction Financing [NO_ZAP_17HPD048X] EAS Date
May 16, 2017
✅ Hpd Construction Financing [NO_ZAP_17HPD048X] Negative Declaration
Jun 29, 2017
HPD Financing ("Project Start")
Nov 07, 2018
Fully Permitted
Dec 10, 2021
Building Completion (HPD)
Dec 10, 2021
Certificate of Occupancy