ROCHESTER SUYDAM PHASE 1
35 ROCHESTER AVENUE (Boro: 3, Block: 1709, Lot: 9)
Brooklyn
Duration
Total Duration:18.8 years
Start Date:Aug 2005
End Date:Jun 2024
RFP Information
New Foundations Homeownership Program Round III RFP
Identifiers
Project ID:44223
Building ID:969695
Data Quality Note
19-36 (Fair)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Aug 29, 2005
RFP Release: New Foundations Homeownership Program Round III RFP
Aug 03, 2016
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [P2017K0240] Earliest EAS Work (Site Survey)
May 31, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [P2017K0240] Lead Agency Letter
Jan 10, 2019
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [P2017K0240] EAS Date
Feb 22, 2019
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [P2017K0240] Negative Declaration
May 04, 2020
Earliest DOB Filing
Jun 30, 2021
HPD Financing ("Project Start")
Aug 20, 2021
Fully Permitted
Jun 11, 2024
Building Completion (HPD)