Duration

Total Duration:9.0 years
Start Date:Sep 2011
End Date:Aug 2020

RFP Information

Seward Park RFP

Identifiers

Project ID:52435
Building ID:969128

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20112013201520172019202120232025ActualOfficialEssex Crossing - Site 6164 BROOME STREET(Boro: 1, Block: 347, Lot: 7501)Manhattan9.0yrs1.9yrs

Timeline Events (16)

Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Zoning Map Amendment + Udaap Designation + Disposition City Owned Property [P2014M0451] Positive Declaration (EIS Required)
Sep 07, 2011
Zoning Special Permit Cpc + Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property + City Map Amendment [P2012M0292] Lead Agency Letter
Sep 07, 2011
Zoning Special Permit Cpc + Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property + City Map Amendment [P2012M0292] EAS Date
Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property + City Map Amendment [P2012M0292] Positive Declaration (EIS Required)
Jan 09, 2013
RFP Release: Seward Park RFP
Sep 18, 2013
✅ RFP Designation: Seward Park RFP
Aug 01, 2014
Zoning Special Permit Cpc + Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property + City Map Amendment [P2012M0292] Earliest EAS Work (Phase 1B Archaeological Survey)
Sep 11, 2014
Earliest DOB Filing
Dec 08, 2015
HPD Financing ("Project Start")
Jan 29, 2016
Fully Permitted
Oct 25, 2017
Certificate of Occupancy
Oct 25, 2017
Building Completion (HPD)
Jan 11, 2019
Zoning Map Amendment + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2018M0127] Earliest EAS Work (Site Survey)
Oct 17, 2019
Zoning Map Amendment + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2018M0127] Lead Agency Letter
Aug 27, 2020
Zoning Map Amendment + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2018M0127] EAS Date
Aug 31, 2020
✅ Zoning Map Amendment + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2018M0127] Negative Declaration