ESSEX CROSSING - SITE 1

242 BROOME STREET (Boro: 1, Block: 409, Lot: 7502)
Manhattan

Duration

Total Duration:6.8 years
Start Date:Sep 2011
End Date:Jul 2018

Identifiers

Project ID:52082
Building ID:968932

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20112013201520172019202120232025ActualOfficialESSEX CROSSING - SITE 1242 BROOME STREET(Boro: 1, Block: 409, Lot: 7502)Manhattan6.8yrs2.6yrs

Timeline Events (9)

Sep 07, 2011
⚠️ Zoning Special Permit Cpc + Udaap Designation + Disposition City Owned Property + Zoning Map Amendment [P2014M0451] Positive Declaration (EIS Required)
Sep 07, 2011
⚠️ Zoning Special Permit Bsa + Zoning Special Permit Cpc + Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + City Map Amendment [P2012M0292] Positive Declaration (EIS Required)
Aug 10, 2012
Zoning Special Permit Bsa + Zoning Special Permit Cpc + Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + City Map Amendment [P2012M0292] Lead Agency Letter
Aug 01, 2014
Zoning Special Permit Bsa + Zoning Special Permit Cpc + Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + City Map Amendment [P2012M0292] Earliest EAS Work (Phase I ESA and Phase II ESI)
Sep 11, 2014
Earliest DOB Filing
Nov 24, 2015
HPD Financing ("Project Start")
Mar 15, 2016
Fully Permitted
Apr 12, 2018
Certificate of Occupancy
Jul 05, 2018
Building Completion (HPD)