Total Duration:13.4 years
Start Date:May 2005
End Date:Sep 2018
Identifiers
Project ID:58954
Building ID:968125
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (12)
May 20, 2005
Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property (Contemplated) + City Map Amendment (Contemplated) [P2007Q0106] Lead Agency Letter
May 20, 2005
Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property (Contemplated) + City Map Amendment (Contemplated) [P2007Q0106] EAS Date
May 20, 2005
⚠️ Zoning Map Amendment + Zoning Text Amendment + Udaap Designation + Disposition City Owned Property (Contemplated) + City Map Amendment (Contemplated) [P2007Q0106] Positive Declaration (EIS Required)
Dec 14, 2015
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) + Other Discretionary Permit (Contemplated) [NO_ZAP_16HPD105Q] Earliest EAS Work (Phase I ESA)
Dec 22, 2015
Earliest DOB Filing
Feb 29, 2016
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) + Other Discretionary Permit (Contemplated) [NO_ZAP_16HPD105Q] Lead Agency Letter
May 26, 2016
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) + Other Discretionary Permit (Contemplated) [NO_ZAP_16HPD105Q] EAS Date
Jun 03, 2016
✅ Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) + Other Discretionary Permit (Contemplated) [NO_ZAP_16HPD105Q] Negative Declaration
Jun 28, 2016
HPD Financing ("Project Start")
Sep 22, 2016
Fully Permitted
May 16, 2018
Certificate of Occupancy
Sep 24, 2018
Building Completion (HPD)