BAM Cultural District North Site Tower II

15 LAFAYETTE AVENUE (Boro: 3, Block: 2107, Lot: 7502)
Brooklyn

Duration

Total Duration:5.3 years
Start Date:Nov 2012
End Date:Mar 2018

RFP Information

BAM Noth Site II Downtown Brooklyn Cultural District RFP

Identifiers

Project ID:51123
Building ID:967799

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2012201420162018202020222024ActualOfficialBAM Cultural District North Site...15 LAFAYETTE AVENUE(Boro: 3, Block: 2107, Lot: 7502)Brooklyn5.3yrs2.9yrs

Timeline Events (15)

Nov 26, 2012
RFP Release: BAM Noth Site II Downtown Brooklyn Cultural District RFP
Mar 12, 2013
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD002K] Earliest EAS Work (Site Survey)
Jul 18, 2013
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD002K] Lead Agency Letter
Oct 08, 2013
✅ RFP Designation: BAM Noth Site II Downtown Brooklyn Cultural District RFP
Oct 16, 2013
✅ Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD002K] Negative Declaration
Oct 17, 2013
Disposition City Owned Property + Zoning Authorization + Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD002K] EAS Date
Oct 25, 2013
Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_14HPD069K] Earliest EAS Work (Phase I ESA)
Apr 04, 2014
Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_14HPD069K] Lead Agency Letter
Sep 26, 2014
Earliest DOB Filing
Jan 09, 2015
Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_14HPD069K] EAS Date
Feb 02, 2015
✅ Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_14HPD069K] Negative Declaration
May 07, 2015
HPD Financing ("Project Start")
Jul 22, 2015
Fully Permitted
Feb 01, 2018
Certificate of Occupancy
Mar 20, 2018
Building Completion (HPD)