St. Albans Cycle Of Life
118-35 FARMERS BOULEVARD (Boro: 4, Block: 12603, Lot: 7501)
Queens
Duration
Total Duration:5.8 years
Start Date:Feb 2013
End Date:Dec 2018
Identifiers
Project ID:55263
Building ID:966134
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (8)
Feb 14, 2013
Earliest DOB Filing
Feb 04, 2014
Variance Bulk [NO_ZAP_14BSA036Q] EAS Date
Sep 23, 2014
✅ Variance Bulk [NO_ZAP_14BSA036Q] Negative Declaration
Oct 03, 2014
Variance Bulk [NO_ZAP_14BSA036Q] Lead Agency Letter
Jun 30, 2016
HPD Financing ("Project Start")
Oct 13, 2016
Fully Permitted
Aug 03, 2018
Building Completion (HPD)
Dec 04, 2018
Certificate of Occupancy