Arker.34-11 Beach Channel Drive

34-11 BEACH CHANNEL DRIVE (Boro: 4, Block: 15950, Lot: 7501)
Queens

Duration

Total Duration:3.5 years
Start Date:Feb 2015
End Date:Aug 2018

Identifiers

Project ID:52937
Building ID:965899

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficialArker.34-11 Beach Channel Drive34-11 BEACH CHANNEL DRIVE(Boro: 4, Block: 15950, Lot: 7501)Queens3.5yrs3.2yrs

Timeline Events (13)

Feb 11, 2015
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_15HPD067Q] Earliest EAS Work (Noise Monitoring)
Feb 11, 2015
Special Permit Bsa + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA064Q] Earliest EAS Work (Noise Monitoring)
Mar 23, 2015
Earliest DOB Filing
Apr 03, 2015
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_15HPD067Q] Lead Agency Letter
Jun 18, 2015
Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_15HPD067Q] EAS Date
Jun 19, 2015
✅ Hpd Construction Financing + Hpd Hdc Program Funding (Contemplated) [NO_ZAP_15HPD067Q] Negative Declaration
Jun 25, 2015
HPD Financing ("Project Start")
Mar 29, 2016
Fully Permitted
Jan 12, 2017
Special Permit Bsa + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA064Q] EAS Date
Jan 13, 2017
Special Permit Bsa + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA064Q] Lead Agency Letter
Aug 08, 2017
✅ Special Permit Bsa + Hpd Construction Financing (Contemplated) [NO_ZAP_17BSA064Q] Negative Declaration
Aug 20, 2018
Certificate of Occupancy
Aug 20, 2018
Building Completion (HPD)