TLK Manor

944 ROGERS PLACE (Boro: 2, Block: 2699, Lot: 7)
Bronx

Duration

Total Duration:4.6 years
Start Date:Oct 2014
End Date:Apr 2019

Identifiers

Project ID:55036
Building ID:965812

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201420162018202020222024ActualOfficialTLK Manor944 ROGERS PLACE(Boro: 2, Block: 2699, Lot: 7)Bronx4.6yrs2.8yrs

Timeline Events (9)

Oct 01, 2014
Hpd Construction Financing [NO_ZAP_15HPD064X] Earliest EAS Work (Phase I ESA)
Dec 01, 2015
Earliest DOB Filing
May 05, 2016
Hpd Construction Financing [NO_ZAP_15HPD064X] EAS Date
May 19, 2016
Hpd Construction Financing [NO_ZAP_15HPD064X] Lead Agency Letter
May 19, 2016
✅ Hpd Construction Financing [NO_ZAP_15HPD064X] Negative Declaration
Jun 29, 2016
HPD Financing ("Project Start")
Nov 03, 2016
Fully Permitted
Aug 17, 2018
Certificate of Occupancy
Apr 29, 2019
Building Completion (HPD)