695 GRAND STREET

695 GRAND STREET (Boro: 3, Block: 2782, Lot: 7502)
Brooklyn

Duration

Total Duration:6.2 years
Start Date:Nov 2012
End Date:Jan 2019

Identifiers

Project ID:50655
Building ID:958176
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2012201420162018202020222024ActualOfficial
695 GRAND STREET695 GRAND STREET(Boro: 3, Block: 2782, Lot: 7502)Brooklyn6.2yrs3.1yrs

Timeline Events (9)

Nov 01, 2012
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0304] Earliest EAS Work (Phase I ESA)
Jan 27, 2014
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0304] Lead Agency Letter
May 28, 2014
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0304] EAS Date
May 28, 2014
✅ Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0304] Negative Declaration
Feb 12, 2015
Earliest DOB Filing
Dec 22, 2015
HPD Financing ("Project Start")
Oct 27, 2016
Fully Permitted
Aug 29, 2018
Certificate of Occupancy
Jan 28, 2019
Building Completion (HPD)