LPC WAREHOUSE/ WILLIAMSBURG BRIDGEVIEW
105 SOUTH 5 STREET (Boro: 3, Block: 2443, Lot: 7501)
Brooklyn
Duration
Total Duration:6.7 years
Start Date:May 2012
End Date:Feb 2019
RFP Information
LPC Warehouse RFP
Identifiers
Project ID:50411
Building ID:958174
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (11)
May 29, 2012
RFP Release: LPC Warehouse RFP
May 22, 2013
✅ RFP Designation: LPC Warehouse RFP
Dec 04, 2014
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0153] Earliest EAS Work (Field Survey)
Dec 15, 2014
Earliest DOB Filing
Mar 05, 2015
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0153] Lead Agency Letter
May 12, 2015
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0153] EAS Date
May 13, 2015
✅ Disposition City Owned Property + Udaap Designation + Hpd Construction Financing [P2014K0153] Negative Declaration
Jun 29, 2016
HPD Financing ("Project Start")
Oct 14, 2016
Fully Permitted
Nov 29, 2018
Certificate of Occupancy
Feb 25, 2019
Building Completion (HPD)