Duration
Total Duration:10.9 years
Start Date:Jan 2006
End Date:Nov 2016
Identifiers
Project ID:51299
Building ID:956539
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Jan 01, 2006
Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Udaap Designation [2022K0289] Earliest EAS Work (Field surveys and data collection)
Feb 06, 2007
Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Udaap Designation [2022K0289] EAS Date
Feb 15, 2007
⚠️ Disposition City Owned Property + Zoning Map Amendment + City Map Amendment + Zoning Special Permit Cpc + Udaap Designation [2022K0289] Positive Declaration (EIS Required)
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment [P2009K0050] Positive Declaration (EIS Required)
Mar 06, 2014
Earliest DOB Filing
Jun 27, 2014
HPD Financing ("Project Start")
Nov 12, 2014
Fully Permitted
Nov 25, 2016
Certificate of Occupancy
Nov 25, 2016
Building Completion (HPD)