Summit Ridge
950 SUMMIT AVENUE (Boro: 2, Block: 2524, Lot: 33)
Bronx
Duration
Total Duration:4.4 years
Start Date:Nov 2012
End Date:Mar 2017
Identifiers
Project ID:52667
Building ID:955526
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Nov 01, 2012
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD015X] Earliest EAS Work (Phase I ESA)
Aug 13, 2014
Earliest DOB Filing
Nov 03, 2014
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD015X] Lead Agency Letter
Dec 05, 2014
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD015X] EAS Date
Dec 08, 2014
✅ Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD015X] Negative Declaration
Dec 18, 2014
HPD Financing ("Project Start")
Apr 20, 2015
Fully Permitted
Mar 31, 2017
Certificate of Occupancy
Mar 31, 2017
Building Completion (HPD)