HELP. 984 Woodycrest Avenue
984 WOODYCREST AVENUE (Boro: 2, Block: 2507, Lot: 15)
Bronx
Duration
Total Duration:3.6 years
Start Date:Jun 2014
End Date:Jan 2018
Identifiers
Project ID:52597
Building ID:955365
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Jun 01, 2014
Hpd Construction Financing [NO_ZAP_15HPD036X] Earliest EAS Work (Phase I ESA)
Mar 20, 2015
Hpd Construction Financing [NO_ZAP_15HPD036X] Lead Agency Letter
Apr 20, 2015
Earliest DOB Filing
Apr 23, 2015
Hpd Construction Financing [NO_ZAP_15HPD036X] EAS Date
Jun 16, 2015
✅ Hpd Construction Financing [NO_ZAP_15HPD036X] Negative Declaration
Nov 17, 2015
HPD Financing ("Project Start")
Mar 30, 2016
Fully Permitted
Jan 11, 2018
Certificate of Occupancy
Jan 11, 2018
Building Completion (HPD)