JERICHO. 2065 WALTON AVENUE

2065 WALTON AVENUE (Boro: 2, Block: 3179, Lot: 60)
Bronx

Duration

Total Duration:7.3 years
Start Date:Feb 2011
End Date:Jun 2018

Identifiers

Project ID:52223
Building ID:954207

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20112013201520172019202120232025ActualOfficialJERICHO. 2065 WALTON AVENUE2065 WALTON AVENUE(Boro: 2, Block: 3179, Lot: 60)Bronx7.3yrs3.0yrs

Timeline Events (10)

Feb 11, 2011
Other Discretionary Permit [P2011X0163] EAS Date
Mar 01, 2014
Hpd Construction Financing [NO_ZAP_15HPD010X] Earliest EAS Work (Phase I ESA)
Jul 08, 2014
Earliest DOB Filing
Aug 28, 2014
Hpd Construction Financing [NO_ZAP_15HPD010X] Lead Agency Letter
Oct 30, 2014
Hpd Construction Financing [NO_ZAP_15HPD010X] EAS Date
Oct 31, 2014
✅ Hpd Construction Financing [NO_ZAP_15HPD010X] Negative Declaration
Jun 02, 2015
Fully Permitted
Jun 03, 2015
HPD Financing ("Project Start")
Jun 05, 2018
Certificate of Occupancy
Jun 05, 2018
Building Completion (HPD)