LIVONIA PHASE II SITES 6-8

453 HINSDALE STREET (Boro: 3, Block: 3818, Lot: 7501)
Brooklyn

Duration

Total Duration:6.5 years
Start Date:Apr 2013
End Date:Sep 2019

RFP Information

Livonia Avenue Initiative Phase II RFP

Identifiers

Project ID:54909
Building ID:953939

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2013201520172019202120232025ActualOfficialLIVONIA PHASE II SITES 6-8453 HINSDALE STREET(Boro: 3, Block: 3818, Lot: 7501)Brooklyn6.5yrs3.2yrs

Timeline Events (11)

Apr 09, 2013
Disposition City Owned Property + Hpd Construction Financing + Zoning Map Amendment + Udaap Designation [P2013K0263] Earliest EAS Work (Noise Monitoring)
May 01, 2013
Disposition City Owned Property + Hpd Construction Financing + Zoning Map Amendment + Udaap Designation [P2013K0263] Lead Agency Letter
Apr 07, 2014
RFP Release: Livonia Avenue Initiative Phase II RFP
Dec 04, 2014
✅ RFP Designation: Livonia Avenue Initiative Phase II RFP
Nov 16, 2015
Earliest DOB Filing
Mar 25, 2016
Disposition City Owned Property + Hpd Construction Financing + Zoning Map Amendment + Udaap Designation [P2013K0263] EAS Date
Mar 29, 2016
✅ Disposition City Owned Property + Hpd Construction Financing + Zoning Map Amendment + Udaap Designation [P2013K0263] Negative Declaration
Jun 30, 2016
HPD Financing ("Project Start")
Nov 07, 2016
Fully Permitted
Sep 26, 2019
Certificate of Occupancy
Sep 26, 2019
Building Completion (HPD)