PS 186 AKA BGCH (BOYS AND GIRLS CLUB OF HARLEM)

525 WEST 145 STREET (Boro: 1, Block: 2077, Lot: 7501)
Manhattan

Duration

Total Duration:14.4 years
Start Date:Jul 2002
End Date:Nov 2016

Identifiers

Project ID:51357
Building ID:951689
Data Quality Note
0-18 (Poor)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
200220062010201420182022ActualOfficial
PS 186 AKA BGCH (BOYS AND GIRLS ...525 WEST 145 STREET(Boro: 1, Block: 2077, Lot: 7501)Manhattan14.4yrs2.4yrs

Timeline Events (7)

Jul 12, 2002
Earliest DOB Filing
Mar 09, 2010
Disposition City Owned Property [NO_ZAP_13HPD014M] Earliest EAS Work (Phase I ESA)
Sep 21, 2012
Disposition City Owned Property [NO_ZAP_13HPD014M] Lead Agency Letter
Oct 05, 2012
Disposition City Owned Property [NO_ZAP_13HPD014M] EAS Date
Oct 05, 2012
✅ Disposition City Owned Property [NO_ZAP_13HPD014M] Negative Declaration
Jul 09, 2014
HPD Financing ("Project Start")
Nov 16, 2016
Building Completion (HPD)