Calvary.112-02 Guy Brewer Boulevard
162-25 112 ROAD (Boro: 4, Block: 12183, Lot: 35)
Queens
Duration
Total Duration:7.5 years
Start Date:Dec 2008
End Date:Jun 2016
Identifiers
Project ID:50495
Building ID:949059
Data Quality Note
37-48 (Good)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (10)
Dec 02, 2008
Zoning Map Amendment [P2008Q0278] Lead Agency Letter
May 07, 2009
Variance Bulk [NO_ZAP_10BSA012Q] Earliest EAS Work (Soil Borings)
Jun 08, 2009
Earliest DOB Filing
Jul 24, 2009
Variance Bulk [NO_ZAP_10BSA012Q] EAS Date
Jan 08, 2010
Variance Bulk [NO_ZAP_10BSA012Q] Lead Agency Letter
Feb 09, 2010
✅ Variance Bulk [NO_ZAP_10BSA012Q] Negative Declaration
Mar 27, 2014
Fully Permitted
Aug 01, 2014
HPD Financing ("Project Start")
Dec 11, 2015
Certificate of Occupancy
Jun 15, 2016
Building Completion (HPD)