UP. 316 East 162nd St.

316 EAST 162 STREET (Boro: 2, Block: 2421, Lot: 27)
Bronx

Duration

Total Duration:8.5 years
Start Date:Jul 2008
End Date:Dec 2016

Identifiers

Project ID:49172
Building ID:948177

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
200820102012201420162018202020222024ActualOfficialUP. 316 East 162nd St.316 EAST 162 STREET(Boro: 2, Block: 2421, Lot: 27)Bronx8.5yrs2.5yrs

Timeline Events (12)

Jul 01, 2008
Zoning Map Amendment + Zoning Text Amendment [P2009X0248] Earliest EAS Work (Site Survey)
Nov 12, 2008
Zoning Map Amendment + Zoning Text Amendment [P2009X0248] EAS Date
Nov 12, 2008
⚠️ Zoning Map Amendment + Zoning Text Amendment [P2009X0248] Positive Declaration (EIS Required)
Jul 26, 2013
Hpd Construction Financing [NO_ZAP_14HPD052X] Earliest EAS Work (Phase I ESA)
Jan 17, 2014
Earliest DOB Filing
Feb 14, 2014
Hpd Construction Financing [NO_ZAP_14HPD052X] Lead Agency Letter
May 09, 2014
Hpd Construction Financing [NO_ZAP_14HPD052X] EAS Date
May 09, 2014
✅ Hpd Construction Financing [NO_ZAP_14HPD052X] Negative Declaration
Jun 26, 2014
HPD Financing ("Project Start")
Mar 23, 2015
Fully Permitted
Dec 13, 2016
Certificate of Occupancy
Dec 13, 2016
Building Completion (HPD)