DOE. 1420 CROTONA PARK EAST

1420 CROTONA PARK EAST (Boro: 2, Block: 2938, Lot: 9)
Bronx

Duration

Total Duration:4.0 years
Start Date:Jan 2013
End Date:Dec 2016

Identifiers

Project ID:50200
Building ID:948174

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2013201520172019202120232025ActualOfficialDOE. 1420 CROTONA PARK EAST1420 CROTONA PARK EAST(Boro: 2, Block: 2938, Lot: 9)Bronx4.0yrs1.7yrs

Timeline Events (9)

Jan 01, 2013
Hpd Construction Financing [NO_ZAP_14HPD055X] Earliest EAS Work (Phase I Environmental Site Assessment)
Apr 04, 2014
Hpd Construction Financing [NO_ZAP_14HPD055X] Lead Agency Letter
Jun 10, 2014
Earliest DOB Filing
Sep 16, 2014
Hpd Construction Financing [NO_ZAP_14HPD055X] EAS Date
Sep 16, 2014
✅ Hpd Construction Financing [NO_ZAP_14HPD055X] Negative Declaration
Mar 26, 2015
HPD Financing ("Project Start")
May 26, 2015
Fully Permitted
Dec 13, 2016
Certificate of Occupancy
Dec 13, 2016
Building Completion (HPD)