Greenpoint Landing E3

33 EAGLE STREET (Boro: 3, Block: 2494, Lot: 7501)
Brooklyn

Duration

Total Duration:4.1 years
Start Date:Apr 2013
End Date:May 2017

Identifiers

Project ID:49938
Building ID:947501

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2013201520172019202120232025ActualOfficialGreenpoint Landing E333 EAGLE STREET(Boro: 3, Block: 2494, Lot: 7501)Brooklyn4.1yrs2.4yrs

Timeline Events (9)

Apr 10, 2013
Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Site Selection Public Facility + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2012K0231] Earliest EAS Work (Traffic Counts, Pedestrian Flow Data Collection)
Jul 19, 2013
Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Site Selection Public Facility + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2012K0231] Lead Agency Letter
Jul 19, 2013
Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Site Selection Public Facility + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2012K0231] EAS Date
Jul 22, 2013
✅ Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Site Selection Public Facility + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc [P2012K0231] Negative Declaration
Mar 03, 2014
Earliest DOB Filing
Oct 21, 2014
Fully Permitted
Dec 23, 2014
HPD Financing ("Project Start")
Oct 28, 2016
Certificate of Occupancy
May 09, 2017
Building Completion (HPD)