NORTH BROOKLYN OPPORTUNITIES (NBO)

7 STAGG STREET (Boro: 3, Block: 3022, Lot: 101)
Brooklyn

Duration

Total Duration:3.4 years
Start Date:Apr 2013
End Date:Sep 2016

Identifiers

Project ID:48775
Building ID:946631

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2013201520172019202120232025ActualOfficialNORTH BROOKLYN OPPORTUNITIES (NB...7 STAGG STREET(Boro: 3, Block: 3022, Lot: 101)Brooklyn3.4yrs1.5yrs

Timeline Events (9)

Apr 12, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Earliest EAS Work (Phase I ESA)
May 14, 2013
Earliest DOB Filing
Oct 08, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Lead Agency Letter
Apr 21, 2014
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] EAS Date
Apr 22, 2014
✅ Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Negative Declaration
Feb 26, 2015
HPD Financing ("Project Start")
Jun 08, 2015
Fully Permitted
Sep 13, 2016
Certificate of Occupancy
Sep 13, 2016
Building Completion (HPD)