NORTH BROOKLYN OPPORTUNITIES (NBO)
568 GRAHAM AVENUE (Boro: 3, Block: 2700, Lot: 6)
Brooklyn
Duration
Total Duration:4.0 years
Start Date:Apr 2013
End Date:Mar 2017
Identifiers
Project ID:48775
Building ID:946629
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Apr 12, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Earliest EAS Work (Phase I ESA)
May 14, 2013
Earliest DOB Filing
Oct 08, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Lead Agency Letter
Apr 21, 2014
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] EAS Date
Apr 22, 2014
✅ Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Negative Declaration
Feb 26, 2015
HPD Financing ("Project Start")
Sep 25, 2015
Fully Permitted
Mar 30, 2017
Certificate of Occupancy
Mar 30, 2017
Building Completion (HPD)