Duration

Total Duration:4.0 years
Start Date:Apr 2013
End Date:Mar 2017

Identifiers

Project ID:48775
Building ID:946629

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2013201520172019202120232025ActualOfficialNORTH BROOKLYN OPPORTUNITIES (NB...568 GRAHAM AVENUE(Boro: 3, Block: 2700, Lot: 6)Brooklyn4.0yrs2.1yrs

Timeline Events (9)

Apr 12, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Earliest EAS Work (Phase I ESA)
May 14, 2013
Earliest DOB Filing
Oct 08, 2013
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Lead Agency Letter
Apr 21, 2014
Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] EAS Date
Apr 22, 2014
✅ Hpd Construction Financing + Udaap Designation (Contemplated) [NO_ZAP_14HPD017K] Negative Declaration
Feb 26, 2015
HPD Financing ("Project Start")
Sep 25, 2015
Fully Permitted
Mar 30, 2017
Certificate of Occupancy
Mar 30, 2017
Building Completion (HPD)