HSI. 213 EAST 203RD STREET
211 EAST 203 STREET (Boro: 2, Block: 3309, Lot: 39)
Bronx
Duration
Total Duration:4.1 years
Start Date:Apr 2018
End Date:Apr 2022
Identifiers
Project ID:67522
Building ID:934463
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Apr 01, 2018
Hpd Construction Financing [NO_ZAP_19HPD074X] Earliest EAS Work (Phase I ESA)
Sep 10, 2018
Earliest DOB Filing
Feb 27, 2019
Hpd Construction Financing [NO_ZAP_19HPD074X] Lead Agency Letter
May 10, 2019
Hpd Construction Financing [NO_ZAP_19HPD074X] EAS Date
May 10, 2019
✅ Hpd Construction Financing [NO_ZAP_19HPD074X] Negative Declaration
Jul 25, 2019
HPD Financing ("Project Start")
Sep 23, 2019
Fully Permitted
Apr 20, 2022
Building Completion (HPD)
Apr 20, 2022
Certificate of Occupancy