Duration
Total Duration:10.0 years
Start Date:Feb 2007
End Date:Feb 2017
Identifiers
Project ID:51299
Building ID:928126
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Feb 01, 2007
Udaap Designation + Disposition City Owned Property + Housing Plan Project [2022K0289] Lead Agency Letter
Feb 06, 2007
Udaap Designation + Disposition City Owned Property + Housing Plan Project [2022K0289] EAS Date
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Housing Plan Project [2022K0289] Positive Declaration (EIS Required)
Feb 15, 2007
⚠️ Udaap Designation + Disposition City Owned Property + Zoning Map Amendment [P2009K0050] Positive Declaration (EIS Required)
Mar 06, 2014
Earliest DOB Filing
Jun 27, 2014
HPD Financing ("Project Start")
Nov 12, 2014
Fully Permitted
Nov 25, 2016
Building Completion (HPD)
Feb 08, 2017
Certificate of Occupancy