ROCHESTER SUYDAM PHASE 1

335 RALPH AVENUE (Boro: 3, Block: 1556, Lot: 3)
Brooklyn

Duration

Total Duration:19.1 years
Start Date:Aug 2005
End Date:Sep 2024

RFP Information

New Foundations Homeownership Program Round III RFP

Identifiers

Project ID:44223
Building ID:927737
Data Quality Note
19-36 (Fair)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20052007200920112013201520172019202120232025ActualOfficial
ROCHESTER SUYDAM PHASE 1335 RALPH AVENUE(Boro: 3, Block: 1556, Lot: 3)Brooklyn19.1yrs3.2yrs

Timeline Events (12)

Aug 29, 2005
RFP Release: New Foundations Homeownership Program Round III RFP
Mar 28, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Earliest EAS Work (Noise Monitoring)
May 04, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Lead Agency Letter
May 04, 2007
Zoning Map Amendment + Zoning Text Amendment [P2007K0317] EAS Date
May 07, 2007
✅ Zoning Map Amendment + Zoning Text Amendment [P2007K0317] Negative Declaration
Feb 22, 2019
✅ Udaap Designation + Disposition City Owned Property [P2017K0240] Negative Declaration
May 07, 2020
Earliest DOB Filing
Jun 30, 2021
HPD Financing ("Project Start")
Aug 19, 2021
Fully Permitted
Oct 05, 2021
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [2025K0235] EAS Date
Oct 07, 2021
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing [2025K0235] Negative Declaration
Sep 24, 2024
Building Completion (HPD)