Duration
Total Duration:4.0 years
Start Date:Nov 2017
End Date:Dec 2021
Identifiers
Project ID:65315
Building ID:927563
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (7)
Nov 27, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [NO_ZAP_18HPD093K] Earliest EAS Work (Phase I ESA)
Mar 05, 2019
Earliest DOB Filing
Feb 24, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [NO_ZAP_18HPD093K] EAS Date
Mar 05, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [NO_ZAP_18HPD093K] Lead Agency Letter
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing + Other Discretionary Permit [NO_ZAP_18HPD093K] Negative Declaration
Jun 30, 2021
HPD Financing ("Project Start")
Dec 07, 2021
Fully Permitted