BED STUY CENTRAL AND NORTH PHASE I

821 WILLOUGHBY AVENUE (Boro: 3, Block: 1589, Lot: 58)
Brooklyn

Duration

Total Duration:7.3 years
Start Date:Nov 2017
End Date:Mar 2025

Identifiers

Project ID:65315
Building ID:927550

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201720182019202020212022202320242025ActualOfficialBED STUY CENTRAL AND NORTH PHASE...821 WILLOUGHBY AVENUE(Boro: 3, Block: 1589, Lot: 58)Brooklyn7.3yrs3.7yrs

Timeline Events (9)

Nov 27, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Earliest EAS Work (Phase I ESA)
Feb 28, 2019
Earliest DOB Filing
Feb 24, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] EAS Date
Mar 05, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Lead Agency Letter
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) [NO_ZAP_18HPD093K] Negative Declaration
Jun 30, 2021
HPD Financing ("Project Start")
Dec 04, 2021
Fully Permitted
Mar 12, 2025
Certificate of Occupancy
Mar 12, 2025
Building Completion (HPD)