THE ROBESON

100 WEST 131 STREET (Boro: 1, Block: 1915, Lot: 7501)
Manhattan

Duration

Total Duration:8.3 years
Start Date:Jan 2014
End Date:Apr 2022

Identifiers

Project ID:51867
Building ID:927152

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
201420162018202020222024ActualOfficialTHE ROBESON100 WEST 131 STREET(Boro: 1, Block: 1915, Lot: 7501)Manhattan8.3yrs3.8yrs

Timeline Events (11)

Jan 01, 2014
Udaap Designation + Disposition City Owned Property + Acquisition City Property [P2015M0237] Earliest EAS Work (Soil Borings)
Jan 01, 2015
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0236] Earliest EAS Work (Phase I ESA)
Feb 02, 2016
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0236] Lead Agency Letter
Aug 11, 2016
✅ Udaap Designation + Disposition City Owned Property + Acquisition City Property [P2015M0237] Negative Declaration
Sep 01, 2016
Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0236] EAS Date
Sep 02, 2016
✅ Zoning Map Amendment + Disposition City Owned Property + Udaap Designation + Zoning Text Amendment + Hpd Construction Financing (Contemplated) [P2015M0236] Negative Declaration
Mar 09, 2017
Earliest DOB Filing
Jun 29, 2018
HPD Financing ("Project Start")
Jul 31, 2018
Fully Permitted
Dec 23, 2020
Certificate of Occupancy
Apr 18, 2022
Building Completion (HPD)