Duration
Total Duration:3.7 years
Start Date:Nov 2016
End Date:Aug 2020
Identifiers
Project ID:63751
Building ID:927005
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (9)
Nov 28, 2016
Earliest DOB Filing
Jan 01, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] Earliest EAS Work (Phase I ESA)
Jun 08, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] Lead Agency Letter
Dec 06, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] EAS Date
Dec 06, 2017
✅ Hpd Construction Financing [NO_ZAP_17HPD109X] Negative Declaration
Apr 11, 2018
Fully Permitted
Jun 22, 2018
HPD Financing ("Project Start")
Aug 13, 2020
Certificate of Occupancy
Aug 13, 2020
Building Completion (HPD)