Duration

Total Duration:3.7 years
Start Date:Nov 2016
End Date:Aug 2020

Identifiers

Project ID:63751
Building ID:927005

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficialMOSHOLU GRAND150 VAN CORTLANDT AVENUE EAST(Boro: 2, Block: 3313, Lot: 7501)Bronx3.7yrs2.1yrs

Timeline Events (9)

Nov 28, 2016
Earliest DOB Filing
Jan 01, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] Earliest EAS Work (Phase I ESA)
Jun 08, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] Lead Agency Letter
Dec 06, 2017
Hpd Construction Financing [NO_ZAP_17HPD109X] EAS Date
Dec 06, 2017
✅ Hpd Construction Financing [NO_ZAP_17HPD109X] Negative Declaration
Apr 11, 2018
Fully Permitted
Jun 22, 2018
HPD Financing ("Project Start")
Aug 13, 2020
Certificate of Occupancy
Aug 13, 2020
Building Completion (HPD)