Duration

Total Duration:3.4 years
Start Date:Feb 2015
End Date:Jun 2018

Identifiers

Project ID:51719
Building ID:878727

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficialThe Pavilion at Locust Manor171-04 BAISLEY BOULEVARD(Boro: 4, Block: 12529, Lot: 239)Queens3.4yrs3.0yrs

Timeline Events (9)

Feb 20, 2015
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD076Q] Earliest EAS Work (Phase I ESA)
Feb 23, 2015
Earliest DOB Filing
May 15, 2015
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD076Q] Lead Agency Letter
Jun 12, 2015
Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD076Q] EAS Date
Jun 15, 2015
✅ Hpd Construction Financing + Hpd Hdc Program Funding [NO_ZAP_15HPD076Q] Negative Declaration
Jun 25, 2015
HPD Financing ("Project Start")
Oct 08, 2015
Fully Permitted
Mar 29, 2018
Certificate of Occupancy
Jun 27, 2018
Building Completion (HPD)