WEST END. 15 W 118TH ST
17 WEST 118 STREET (Boro: 1, Block: 1717, Lot: 22)
Manhattan
Duration
Total Duration:4.0 years
Start Date:Jul 2019
End Date:Aug 2023
Identifiers
Project ID:68892
Building ID:805885
Data Quality Note
0-18 (Poor)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (6)
Jul 30, 2019
Hpd Construction Financing [NO_ZAP_20HPD049M] Earliest EAS Work (Phase I ESA, Site Reconnaissance)
Sep 21, 2020
Hpd Construction Financing [NO_ZAP_20HPD049M] Lead Agency Letter
Sep 22, 2020
Hpd Construction Financing [NO_ZAP_20HPD049M] EAS Date
Oct 21, 2020
✅ Hpd Construction Financing [NO_ZAP_20HPD049M] Negative Declaration
Aug 25, 2021
HPD Financing ("Project Start")
Aug 14, 2023
Building Completion (HPD)