201-207 7TH AVENUE (ANCP)

207 7 AVENUE (Boro: 1, Block: 797, Lot: 80)
Manhattan

Duration

Total Duration:5.4 years
Start Date:Jan 2018
End Date:May 2023

Identifiers

Project ID:50204
Building ID:3691

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20182019202020212022202320242025ActualOfficial201-207 7TH AVENUE (ANCP)207 7 AVENUE(Boro: 1, Block: 797, Lot: 80)Manhattan8.0+yrs3.5+yrs

Timeline Events (7)

Jan 01, 2018
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2018M0308] Earliest EAS Work (Phase I ESA)
Sep 28, 2018
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2018M0308] Lead Agency Letter
Jan 25, 2019
Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2018M0308] EAS Date
Jan 25, 2019
✅ Disposition City Owned Property + Udaap Designation + Hpd Construction Financing (Contemplated) [P2018M0308] Negative Declaration
Oct 01, 2021
Earliest DOB Filing
Jun 30, 2022
HPD Financing ("Project Start")
May 31, 2023
Fully Permitted