Duration

Total Duration:6.5 years
Start Date:Nov 2015
End Date:Apr 2022

Identifiers

Project ID:61290
Building ID:342273
Data Quality Note
0-18 (Poor)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficial
ICL. 50 NEVINS STREET50 NEVINS STREET(Boro: 3, Block: 172, Lot: 7501)Brooklyn6.5yrs3.1yrs

Timeline Events (6)

Nov 01, 2015
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Funding Programs (Contemplated) [P2015K0118] Earliest EAS Work (Phase I ESA)
Feb 24, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Funding Programs (Contemplated) [P2015K0118] Lead Agency Letter
Mar 31, 2017
Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Funding Programs (Contemplated) [P2015K0118] EAS Date
Apr 03, 2017
✅ Zoning Map Amendment + Zoning Text Amendment + Hpd Construction Financing (Contemplated) + Funding Programs (Contemplated) [P2015K0118] Negative Declaration
Mar 26, 2019
HPD Financing ("Project Start")
Apr 13, 2022
Building Completion (HPD)