JERICHO.407-409 & 450 E 158TH ST

450 EAST 158 STREET (Boro: 2, Block: 2379, Lot: 45)
Bronx

Duration

Total Duration:1.3 years
Start Date:Dec 2022
End Date:Mar 2024

Identifiers

Project ID:70483
Building ID:1012611

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2022202320242025ActualOfficialJERICHO.407-409 & 450 E 158TH ST450 EAST 158 STREET(Boro: 2, Block: 2379, Lot: 45)Bronx3.0+yrs1.7+yrs

Timeline Events (7)

Dec 07, 2022
Hpd Construction Financing [NO_ZAP_23HPD029X] Earliest EAS Work (Phase I ESA, Noise Monitoring, Site Photography)
Dec 23, 2022
Earliest DOB Filing
Apr 04, 2023
Hpd Construction Financing [NO_ZAP_23HPD029X] Lead Agency Letter
Aug 01, 2023
Hpd Construction Financing [NO_ZAP_23HPD029X] EAS Date
Sep 06, 2023
✅ Hpd Construction Financing [NO_ZAP_23HPD029X] Negative Declaration
Oct 17, 2023
Fully Permitted
Mar 27, 2024
HPD Financing ("Project Start")