HOUSING WORKS. 806 NINTH AVENUE. THE LIRIO
364 WEST 54 STREET (Boro: 1, Block: 1044, Lot: 15)
Manhattan
Duration
Total Duration:15.7 years
Start Date:Sep 2008
End Date:Apr 2024
RFP Information
Clinton/Hell's Kitchen RFP
Identifiers
Project ID:69183
Building ID:1011819
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (12)
Sep 02, 2008
Disposition City Owned Property + Zoning Special Permit Bsa (Contemplated) + Udaap Designation [P2009M0289] Lead Agency Letter
Sep 02, 2008
⚠️ Disposition City Owned Property + Zoning Special Permit Bsa (Contemplated) + Udaap Designation [P2009M0289] Positive Declaration (EIS Required)
Sep 04, 2008
Disposition City Owned Property + Zoning Special Permit Bsa (Contemplated) + Udaap Designation [P2009M0289] EAS Date
Apr 09, 2018
RFP Release: Clinton/Hell's Kitchen RFP
Feb 13, 2019
✅ RFP Designation: Clinton/Hell's Kitchen RFP
Aug 30, 2019
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Acquisition City Property + Hpd Construction Financing (Contemplated) [2020M0112] Earliest EAS Work (Phase I ESA)
Aug 25, 2021
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Acquisition City Property + Hpd Construction Financing (Contemplated) [2020M0112] Lead Agency Letter
Dec 23, 2021
Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Acquisition City Property + Hpd Construction Financing (Contemplated) [2020M0112] EAS Date
Dec 23, 2021
✅ Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Disposition City Owned Property + Acquisition City Property + Hpd Construction Financing (Contemplated) [2020M0112] Negative Declaration
Oct 27, 2022
Earliest DOB Filing
Mar 27, 2024
HPD Financing ("Project Start")
Apr 26, 2024
Fully Permitted