ROCKAWAY VILLAGE PHASE 5

14-12 AUGUSTINA AVENUE
Queens

Duration

Total Duration:1.8 years
Start Date:Mar 2022
End Date:Dec 2023

Identifiers

Project ID:64887
Building ID:1011389
Data Quality Note
19-36 (Fair)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2022202320242025ActualOfficial
ROCKAWAY VILLAGE PHASE 514-12 AUGUSTINA AVENUEQueens3.8+yrs2.0+yrs

Timeline Events (2)

Mar 22, 2022
Earliest DOB Filing
Dec 22, 2023
Project Start (HPD)