COMUNILIFE. 2444 TIEBOUT AVENUE

2444 TIEBOUT AVENUE (Boro: 2, Block: 3022, Lot: 54)
Bronx

Duration

Total Duration:0.8 years
Start Date:Jul 2023
End Date:May 2024

Identifiers

Project ID:73229
Building ID:1010075

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
202320242025ActualOfficialCOMUNILIFE. 2444 TIEBOUT AVENUE2444 TIEBOUT AVENUE(Boro: 2, Block: 3022, Lot: 54)Bronx2.4+yrs1.6+yrs

Timeline Events (7)

Jul 28, 2023
Hpd Construction Financing [NO_ZAP_24HPD019X] Earliest EAS Work (Site Survey)
Aug 30, 2023
Earliest DOB Filing
Mar 14, 2024
Hpd Construction Financing [NO_ZAP_24HPD019X] Lead Agency Letter
Mar 15, 2024
Hpd Construction Financing [NO_ZAP_24HPD019X] EAS Date
Mar 15, 2024
✅ Hpd Construction Financing [NO_ZAP_24HPD019X] Negative Declaration
Apr 22, 2024
Fully Permitted
May 03, 2024
HPD Financing ("Project Start")