SPOFFORD DETENTION CENTER PHASE 2

1223 SPOFFORD AVENUE (Boro: 2, Block: 2738, Lot: 2)
Bronx

Duration

Total Duration:7.8 years
Start Date:Jun 2016
End Date:Mar 2024

Identifiers

Project ID:63757
Building ID:1008198

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
2016201720182019202020212022202320242025ActualOfficialSPOFFORD DETENTION CENTER PHASE ...1223 SPOFFORD AVENUE(Boro: 2, Block: 2738, Lot: 2)Bronx9.6+yrs2.5+yrs

Timeline Events (7)

Jun 01, 2016
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Earliest EAS Work (Phase I ESA)
May 23, 2017
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Lead Agency Letter
May 23, 2017
Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] EAS Date
May 23, 2017
⚠️ Disposition City Owned Property + Zoning Map Amendment + Zoning Text Amendment + Zoning Special Permit Cpc + Hpd Construction Financing (Contemplated) [P2017X0037] Positive Declaration (EIS Required)
Nov 20, 2020
Earliest DOB Filing
Jun 28, 2023
HPD Financing ("Project Start")
Mar 13, 2024
Fully Permitted