HOUSING PLUS. 797 GLENMORE AVE. SHEPHERD-GLENMORE

365 SHEPHERD AVENUE (Boro: 3, Block: 3989, Lot: 1)
Brooklyn

Duration

Total Duration:10.2 years
Start Date:Feb 2015
End Date:Apr 2025

Identifiers

Project ID:71445
Building ID:1006212
Data Quality Note
19-36 (Fair)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
20152016201720182019202020212022202320242025ActualOfficial
HOUSING PLUS. 797 GLENMORE AVE. ...365 SHEPHERD AVENUE(Boro: 3, Block: 3989, Lot: 1)Brooklyn10.2yrs3.2+yrs

Timeline Events (6)

Feb 03, 2015
Zoning Map Amendment + Zoning Text Amendment + Udaap Designation [P2015K0246] Lead Agency Letter
Feb 03, 2015
⚠️ Zoning Map Amendment + Zoning Text Amendment + Udaap Designation [P2015K0246] Positive Declaration (EIS Required)
Nov 15, 2021
Earliest DOB Filing
Oct 19, 2022
HPD Financing ("Project Start")
Jan 17, 2023
Fully Permitted
Apr 24, 2025
Certificate of Occupancy