Duration

Total Duration:22.4 years
Start Date:Jun 2002
End Date:Oct 2024

Identifiers

Project ID:63260
Building ID:1006138
Data Quality Note
37-48 (Good)

Development Timeline

DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
200220062010201420182022ActualOfficial
ENNIS FRANCIS III B1212 WEST 124 STREET(Boro: 1, Block: 1929, Lot: 57)Manhattan22.4yrs1.8yrs

Timeline Events (21)

Jun 01, 2002
Zoning Map Amendment [P2003M0369] Earliest EAS Work (Site Survey)
Apr 17, 2003
Zoning Map Amendment [P2003M0369] EAS Date
Apr 21, 2003
Zoning Map Amendment [P2003M0369] Lead Agency Letter
Apr 21, 2003
✅ Zoning Map Amendment [P2003M0369] Negative Declaration
May 01, 2009
Zoning Special Permit Cpc [P1984M0079] Earliest EAS Work (Phase I ESA)
May 01, 2009
Zoning Special Permit Cpc [P2010M0238] Earliest EAS Work (Phase I ESA)
Jul 26, 2010
Zoning Special Permit Cpc [P1984M0079] Lead Agency Letter
Jul 26, 2010
Zoning Special Permit Cpc [P1984M0079] EAS Date
Jul 26, 2010
Zoning Special Permit Cpc [P2010M0238] Lead Agency Letter
Jul 26, 2010
Zoning Special Permit Cpc [P2010M0238] EAS Date
Sep 27, 2010
✅ Zoning Special Permit Cpc [P1984M0079] Negative Declaration
Sep 27, 2010
✅ Zoning Special Permit Cpc [P2010M0238] Negative Declaration
Aug 08, 2017
Zoning Special Permit Cpc [P2016M0199] Earliest EAS Work (Equipment Calibration)
Jul 02, 2018
Earliest DOB Filing
Aug 23, 2018
Zoning Special Permit Cpc [P2016M0199] Lead Agency Letter
Jan 25, 2019
Zoning Special Permit Cpc [P2016M0199] EAS Date
Jan 28, 2019
✅ Zoning Special Permit Cpc [P2016M0199] Negative Declaration
Feb 11, 2021
Fully Permitted
Dec 20, 2022
HPD Financing ("Project Start")
May 30, 2023
Certificate of Occupancy
Oct 02, 2024
Building Completion (HPD)