BED STUY CENTRAL AND NORTH PHASE II
121 VERNON AVENUE (Boro: 3, Block: 1755, Lot: 56)
Brooklyn
Duration
Total Duration:17.8 years
Start Date:Feb 2006
End Date:Dec 2023
Identifiers
Project ID:68222
Building ID:1005399
Data Quality Note
19-36 (Fair)
Development Timeline
DOB Filing
HPD Financing
Certificate of Occupancy
Building Completion
Fully Permitted
Environmental (EAS/EIS)
Other Milestone
Timeline Events (8)
Feb 22, 2006
Udaap Designation + Disposition City Owned Property [P2006K0271] Lead Agency Letter
Jul 27, 2007
Earliest DOB Filing
Nov 27, 2017
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc (Contemplated) [NO_ZAP_18HPD093K] Earliest EAS Work (Phase I ESA)
Nov 22, 2019
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc (Contemplated) [NO_ZAP_18HPD093K] Lead Agency Letter
Feb 24, 2020
Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc (Contemplated) [NO_ZAP_18HPD093K] EAS Date
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property [2018K0517] Negative Declaration
Mar 05, 2020
✅ Udaap Designation + Disposition City Owned Property + Hpd Construction Financing (Contemplated) + Zoning Special Permit Cpc (Contemplated) [NO_ZAP_18HPD093K] Negative Declaration
Dec 12, 2023
HPD Financing ("Project Start")